Wednesday, December 5, 2018

12/02 - 12/09

As for the last week of the semester, the motor team is pretty much on track with the time schedule. Our main dependency is the motor itself, as we are waiting for it to arrive any time within the next week. Since this week is the last meeting, we decided to split up tasks that we can do throughout the break. Referring to the team's Gantt Chart, I will be looking for machine shops around the South Bay and compare service quotes from them. Then, if the machinists do not approve the materials that we are planning to use, I will be researching other materials that might not cost too expensive.